Jiemeng Intelligent Equipment Headquarters and Production Base Steel Structure and Curtain Wall Project


Location: North side of Yuwotou Avenue and west side of Nansha Avenue, Dongyong Town, Nansha District, Guangzhou City

 

As a leading enterprise in the new energy lithium battery industry, Jiemeng Intelligent Manufacturing's headquarters production base is designed and constructed in accordance with high standard factory requirements. The main structure is a 4-storey steel structure, with a total construction area of 42,316 square meters, including 41,716 square meters for Building 1 and 600 square meters for the roof steel structure and canopy framework of Building 2. The total amount of steel used in the steel structure of Building 1 is 4,780 tons. The floor slab is a composite floor slab, using a closed floor support plate. The steel structure roof adopts water slope drainage, and the roof panel uses 0.6mm aluminum zinc plated original color plate. The bottom is equipped with insulation cotton and stainless steel wire mesh. The wall body is made of 75 thick 1000 type rock wool polyurethane sandwich panel, and the corners of the wall body are all made of integrated formed panels. The window glass is made of LOW-E hollow energy-saving glass; The roof of Building 2 is equipped with double slope drainage and stainless steel water tank. The roof is made of 0.6mm/aluminum zinc plated original color board, and the bottom is equipped with insulation cotton and stainless steel wire mesh. The rain shelter is made of steel structure framework.

 

Due to the characteristics of the design drawings, the construction of Building 1 needs to be carried out in a sequential manner between civil engineering and steel structure. The main body and floor support plate processes of the second and third floors are completed, and then handed over to civil engineering construction, and then handed over to steel structure construction, repeating the cycle. Despite facing numerous difficulties, we actively cooperated with the general contractor and successfully completed the successful topping up of Building 1 on June 3rd. Due to the narrow underground roads, the installation efficiency of the wall framework and wall panels in the later stage is low. The project department and team can only adopt the construction method of cutting corners and extending work hours by working overtime at night. We closely follow the handover of the civil engineering part of the work on site, and timely add manpower and mechanical equipment. At the same time, during the rush period, we strictly control the principle of concealing after passing the acceptance inspection to ensure that the procedures are in place and the quality is satisfactory.

Classification:

Location: North side of Yuwotou Avenue and west side of Nansha Avenue, Dongyong Town, Nansha District, Guangzhou City

 

As a leading enterprise in the new energy lithium battery industry, Jiemeng Intelligent Manufacturing's headquarters production base is designed and constructed in accordance with high standard factory requirements. The main structure is a 4-storey steel structure, with a total construction area of 42,316 square meters, including 41,716 square meters for Building 1 and 600 square meters for the roof steel structure and canopy framework of Building 2. The total amount of steel used in the steel structure of Building 1 is 4,780 tons. The floor slab is a composite floor slab, using a closed floor support plate. The steel structure roof adopts water slope drainage, and the roof panel uses 0.6mm aluminum zinc plated original color plate. The bottom is equipped with insulation cotton and stainless steel wire mesh. The wall body is made of 75 thick 1000 type rock wool polyurethane sandwich panel, and the corners of the wall body are all made of integrated formed panels. The window glass is made of LOW-E hollow energy-saving glass; The roof of Building 2 is equipped with double slope drainage and stainless steel water tank. The roof is made of 0.6mm/aluminum zinc plated original color board, and the bottom is equipped with insulation cotton and stainless steel wire mesh. The rain shelter is made of steel structure framework.

 

Due to the characteristics of the design drawings, the construction of Building 1 needs to be carried out in a sequential manner between civil engineering and steel structure. The main body and floor support plate processes of the second and third floors are completed, and then handed over to civil engineering construction, and then handed over to steel structure construction, repeating the cycle. Despite facing numerous difficulties, we actively cooperated with the general contractor and successfully completed the successful topping up of Building 1 on June 3rd. Due to the narrow underground roads, the installation efficiency of the wall framework and wall panels in the later stage is low. The project department and team can only adopt the construction method of cutting corners and extending work hours by working overtime at night. We closely follow the handover of the civil engineering part of the work on site, and timely add manpower and mechanical equipment. At the same time, during the rush period, we strictly control the principle of concealing after passing the acceptance inspection to ensure that the procedures are in place and the quality is satisfactory.

Key Words:

Jiemeng Intelligent Equipment Headquarters and Production Base Steel Structure and Curtain Wall Project

Previous: Lin's Home Component and Intelligent Warehousing Construction Project

Next: Qicha Community Sports Center and Parking Lot Project

Contact us to learn more about our business solutions

Fill out the form below to receive relevant news and industry insights delivered directly to your inbox

Submit Message