Lin's Wood Industry Smart Dispatching Center (South China) Project Phase I_Guangdong CHINESTAR Steel Structure Co.,Ltd.

logo
搜索
确认
取消
/
/
Lin's Wood Industry Smart Dispatching Center (South China) Project Phase I

Lin's Wood Industry Smart Dispatching Center (South China) Project Phase I

The first phase of Lin's Wood Smart Dispatching Center (South China) project is the first time that Lin's Wood Group has built a logistics and storage park in South China, with a total area of ​​250,000 square meters. This project is located in Huangji Village, Jiujiang Town, Nanhai District, Foshan City. It is mainly a portal type light steel frame structure. The main body is a single-layer steel structure. The wall and roof systems (including thermal insulation cotton), daylighting panels and canopy and other building systems are all For the production and installation of components, the roof adopts siphon drainage. The first phase has a construction area of ​​73561.53 square meters, a maximum span of 24 meters, and a building height of 15.5 meters. The construction of the project started on July 16, 2017 and was completed in October 2017. It lasted 99 days. Due to the tight schedule, many construction procedures were not completed in the early stage of the main steel structure construction, resulting in simultaneous construction procedures and There are many construction units. A series of pile foundations, earth backfilling, concrete pre-burying and pouring, steel structure main body hoisting and maintenance installation, fire-fighting pipelines, water supply and drainage, water and electricity installation, ground concrete pouring, shelf installation, etc. The streamlined operation scene of the construction unit at the same time has brought great construction difficulties to our steel structure installation, especially the secondary transfer of materials and the delivery of the construction work surface. In order to hand over to Party A for use as soon as possible in accordance with the contract period, each process is completed in advance, and aluminum windows and sliding doors are installed at the same time as the steel structure wall panels are installed. During the construction process, it experienced continuous high temperature weather and four typhoons. Every day, workers suffered minor heat stroke. The project department took a series of measures such as taking turns to rest and preventing heatstroke to ensure the installation progress. Before the arrival of each typhoon, all the installation workers were evacuated to nearby hotels and other unfavorable conditions. With the joint efforts of the company and the project department, the contract construction period was completed on time and in quality. No safety and quality accidents occurred during the construction process. Therefore, it has been highly praised and recognized by the civil engineering and the owner. The owner also handed over the 120,000 square meter steel structure project of the second phase project to Zhongchen Company for construction. Project Name: Lin's Wood Industry Smart Dispatching Center (South China) Project Phase I Project Manager: Fan Preliminary Designer: Yang Chunqiang Pre-settlement Clerk: Chen Liren Construction Supervisor: Cheng Fangde Quality Security Officer: Chen Qiji Class Group: Liu Jianhua, Mo Bingrong
Retail price
0.0
Market price
0.0
Number of views:
1000
Product serial number
Quantity
-
+
1
1/1
Number of views:
1000
产品描述

The first phase of Lin's Wood Smart Dispatching Center (South China) project is the first time that Lin's Wood Group has built a logistics and storage park in South China, with a total area of ​​250,000 square meters. This project is located in Huangji Village, Jiujiang Town, Nanhai District, Foshan City. It is mainly a portal type light steel frame structure. The main body is a single-layer steel structure. The wall and roof systems (including thermal insulation cotton), daylighting panels and canopy and other building systems are all For the production and installation of components, the roof adopts siphon drainage. The first phase has a construction area of ​​73561.53 square meters, a maximum span of 24 meters, and a building height of 15.5 meters.

The construction of the project started on July 16, 2017 and was completed in October 2017. It lasted 99 days. Due to the tight schedule, many construction procedures were not completed in the early stage of the main steel structure construction, resulting in simultaneous construction procedures and There are many construction units. A series of pile foundations, earth backfilling, concrete pre-burying and pouring, steel structure main body hoisting and maintenance installation, fire-fighting pipelines, water supply and drainage, water and electricity installation, ground concrete pouring, shelf installation, etc. The streamlined operation scene of the construction unit at the same time has brought great construction difficulties to our steel structure installation, especially the secondary transfer of materials and the delivery of the construction work surface. In order to hand over to Party A for use as soon as possible in accordance with the contract period, each process is completed in advance, and aluminum windows and sliding doors are installed at the same time as the steel structure wall panels are installed. During the construction process, it experienced continuous high temperature weather and four typhoons. Every day, workers suffered minor heat stroke. The project department took a series of measures such as taking turns to rest and preventing heatstroke to ensure the installation progress. Before the arrival of each typhoon, all the installation workers were evacuated to nearby hotels and other unfavorable conditions. With the joint efforts of the company and the project department, the contract construction period was completed on time and in quality. No safety and quality accidents occurred during the construction process. Therefore, it has been highly praised and recognized by the civil engineering and the owner. The owner also handed over the 120,000 square meter steel structure project of the second phase project to Zhongchen Company for construction.

Project Name: Lin's Wood Industry Smart Dispatching Center (South China) Project Phase I

Project Manager: Fan Preliminary Designer: Yang Chunqiang

Pre-settlement Clerk: Chen Liren Construction Supervisor: Cheng Fangde

Quality Security Officer: Chen Qiji Class Group: Liu Jianhua, Mo Bingrong